ARTICLE · 27 OCTOBER 2023

When Is An Old Project A New Project (Or Vice Versa)? The Strange Case Of Grassy Mountain

On September 6, 2023, the Alberta Energy Regulator (the "AER") received a coal exploration and deep-drilling permit application (the "Applications") from Northback Holdings Ltd. (formerly Benga Mining Ltd.) ("Northback").

CanadaEnergy and Natural Resources

On September 6, 2023, the Alberta Energy Regulator (the "AER") received a coal exploration and deep-drilling permit application (the "Applications") from Northback Holdings Ltd. (formerly Benga Mining Ltd.) ("Northback"). The Applications are for a proposed coal development in Crowsnest Pass, known as the Grassy Mountain Coal Project (the "Project").

More specifically, the deep-drilling permit is explained as being for the purpose of drilling "to depths deeper than 150 metres and no deeper than 550 metres on a combination of Crown land and Northback's privately owned land, commencing on October 15, 2023."

October 15, 2023, has now passed, and there has been no apparent decision from the AER with respect to Northback's Applications for the Project. It is unclear what the status of the Applications is and whether, with its Project commencement date of October 15 having passed, Northback intends to proceed with the Project this year.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from