On March 6, 2024, the Alberta government proclaimed the Electricity Statutes
(Modernizing Alberta's Electricity Grid) Amendment Act,
2022 (ESAA). The ESAA amends associated statutes and
regulations such as the Alberta Utilities Commission
Act, Electric Utilities
Act and Hydro and Electric Energy Act.
As part of these changes, the Alberta Utilities Commission (AUC)
published Bulletin
2024-04 to announce the coming into force of an
updated Hydro and Electric
Energy Regulation (HEER). The updates to the HEER
will impact owners of, and applicants for, power plants, energy
storage facilities, transmission lines and distribution
systems.
Background
A previous iteration of the ESAA was introduced to the Alberta
Legislature on November 17, 2021, as Bill 86, Electricity
Statutes Amendment Act, 2021. As we discussed at the time,
through the new act, the government sought to modernize the Alberta
electricity system in the context of rapidly evolving technology
and