ARTICLE · 11 OCTOBER 2024

Update: First Solar RFP In Québec By December 31, 2024

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

Built on a unique model of collaboration, innovation and efficiency, McCarthy Tétrault delivers...

View firm profile
Explore more from McCarthy Tétrault

As reported in our previous post last spring, the Québec Government announced on March 26, 2024 that it would set aside a block of 300 MW for an upcoming solar energy procurement by Hydro-Québec.

CanadaEnergy and Natural Resources

As reported in our previous post last spring, the Québec Government announced on March 26, 2024 that it would set aside a block of 300 MW for an upcoming solar energy procurement by Hydro-Québec.

On September 18 2024, official details of the RFP were released in an order-in-council published in the Gazette officielle du Québec. The enacted regulation requires Hydro-Quebec to hold two calls for tenders, as early as December 31, 2024 for a minimum of 150 MW, and the other by December 31, 2026 for the remaining balance. In addition, all 300 MW procured in the context of those RFPs are required to be interconnected to the Hydro-Québec grid by December 31, 2029.

To manage the variable production output of solar energy, the RFP indicates that solar energy production will be supported by a balancing and supplementary power service, in the form of an energy integration agreement for variable energy which would be secured with either Hydro-Québec or another energy producer

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from