Burnaby submitted there is no real conflict between s. 73(a) and the bylaws, so an analysis of interjurisdictional immunity or paramountcy is largely unnecessary.

CanadaEnergy and Natural Resources

On October 9, 2014, the National Energy Board (the "NEB") heard oral argument for a motion by Trans Mountain Pipeline ULC ("Trans Mountain") seeking an order pursuant to sections 12, 13, and 73(a) of the National Energy Board Act (the "Act"). Submissions were made by Trans Mountain and the City of Burnaby ("Burnaby").  At the end of the hearing, the NEB advised a decision will be made soon, but did not provide a specific time frame.

1.       Background

On August 19, 2014, the NEB issued Ruling No. 28 (the "Ruling"). The Ruling concluded that under s. 73(a) of the Act, Trans Mountain is permitted to enter any Crown (federal or provincial) or private lands which lie in the intended route of its pipeline to carry out surveys and examinations. This included a small portion of the Burnaby Mountain Conservation Area (the "Subject Lands").