Share on LinkedInShare on LinkedIn

ARTICLE · 06 AUGUST 2014

The National Energy Board Considers The Set-Aside And Collection Mechanisms For Abandonment Costs Of NEB-Regulated Pipelines

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In 2008, the National Energy Board identified a proposed approach to address what came to be known as the Land Matters Consultative Initiative, or LMCI.

CanadaEnergy and Natural Resources

In 2008, the National Energy Board (NEB) identified a proposed approach to address what came to be known as the Land Matters Consultative Initiative, or LMCI. There were four distinct streams, with Stream 3 focusing on the financial issues related to pipeline abandonment. The NEB considered the optimal way to ensure that funds will be available when abandonment costs are incurred for decommissioned pipeline infrastructure under its regulatory purview.

In its Reasons for Decision RH-2-2008, issued in May of 2009, the NEB set out guiding principles and considerations and a list of attributes for any mechanism that would be used to set aside funds for pipeline abandonment. It also established a five-year Action Plan for companies to follow. Regulated companies were directed to begin setting aside abandonment funds in the first toll year after May 2014. In RH-2-2008, a base case was included which pipeline companies could use when preparing their preliminary