Two recent cases have highlighted a serious weakness in the governance of the electricity sector in Ontario. The cases illustrate not just the immediate adverse effects of Government ...

CanadaEnergy and Natural Resources

I Introduction

Two recent cases have highlighted a serious weakness in the governance of the electricity sector in Ontario. The cases illustrate not just the immediate adverse effects of Government interference in specific matters but the deeper damage the Government's role does to governance of the sector as a whole.

The first case involves the denial by state regulatory authorities in the United States of the attempt by Hydro One Limited ("Hydro One") to acquire the shares of Avista Corporation ("Avista"), (referred to hereinafter as the "Avista Case"). The second case is the Province's intervention in the applications to the Ontario Energy Board ("OEB") for approval of leave-to-construct ("LTC") a transmission line in northwestern Ontario (referred to hereinafter as the "East-West Tie" or "EWT" case).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from