Power Purchase Agreements (PPAs) provide for the purchase of
electricity, usually by a utility or corporation, from an
independent power producer (IPP). How will recent cancellations of
PPAs in Ontario impact future PPAs anticipated in Saskatchewan and
Alberta?
On July 13, 2018, Ontario's new Progressive Conservative
government followed up on its campaign promises and announced the
termination of 758 renewable energy projects for which the
Independent Electricity System Operator (IESO) contracts had not
yet been finalized. Additionally, the 18.5-megawatt White Pines
Wind Project (the White Pines Project), which had been undergoing
development over the past 10 years and recently received final
approval for construction from IESO in May, was cancelled. In
response to this announcement, the developer indicated that it may
seek to recover the estimated $100 million that it has sunk into
the White Pines Project to date. In order to cancel the White Pines
Project contract,