ARTICLE · 20 AUGUST 2019

SCC Denies Tsilhqot'in Nation Appeal In Taseko Dispute

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

McCarthy Tétrault LLP provides a broad range of legal services, delivering strategic and...

View firm profile
Explore more from McCarthy Tétrault

On June 13, 2019, the Supreme Court of Canada denied leave to appeal of a dispute between Taseko Mines Ltd. ("Taseko"),

CanadaEnergy and Natural Resources

On June 13, 2019, the Supreme Court of Canada denied leave to appeal of a dispute between Taseko Mines Ltd. ("Taseko"), the Province of British Columbia and the Tsilhqot'in Nation relating to the Province's permit approval for Taseko to perform exploratory drilling.

Background

The dispute has its origins in the efforts of Taseko to obtain approval for a mining development known as the Prosperity Project. Under the proposed Prosperity Project, Taseko planned to develop an area 125 km southwest of Williams Lake, BC, in which it owned a mineral lease and mineral claims. Taseko claims that the area contains an estimated 11 million ounces of gold and four billion pounds of copper. At the Supreme Court of Canada in 2014, the Tsilhqot'in Nation had established legal rights to hunt and trap in the area (2014 SCC 44).To commence work on the Prosperity Project under provincial and federal legislation, Taseko had to obtain provincial and federal approval. Obtaining such

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from