Share on LinkedInShare on LinkedIn

ARTICLE · 08 JANUARY 2014

Ruling: Wind Turbine Approvals Comply With The Charter

The Environmental Review Tribunal has approved another wind farm, in Bovaird v. Director, Ministry of the Environment, Case Nos.: 13-070 to 13-075.

CanadaEnergy and Natural Resources

The Environmental Review Tribunal has approved another wind farm, in Bovaird v. Director, Ministry of the Environment, Case Nos.: 13-070 to 13-075. The Dufferin Wind Power Project, in the Township of Melancthon, County of Dufferin, is now approved to build 49 wind turbines with the capacity to generate 91.4 MW of power annually. As part of its approval, the Tribunal decided, for the first time, that the Environmental Protection Act rules for wind turbine approvals do comply with the Canadian Charter of Rights and Freedoms (the "Charter"). Good news for green energy, and for those who care about climate change.

In many previous cases, wind opponents have lost because they cannot prove that wind turbines, built in accordance with the EPA and its regulations, are likely to cause harm to human health. This is the statutory test they must meet. Wind opponents therefore now argue that the renewable energy approval process established by the EPA violates their right to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from