ARTICLE · 20 NOVEMBER 2012

Renewable Energy Approvals Regulations Amended Again

The Ontario Ministry of the Environment has made more amendments to O. Reg. 359/09, the Renewable Energy Approvals Regulation.

CanadaEnergy and Natural Resources

The Ontario Ministry of the Environment has made more amendments to O. Reg. 359/09, the Renewable Energy Approvals Regulation. As a result of concerns raised during the last round of amendments (July 1), these amendments focus on:

  • Re-issuance of draft site plans to reflect changes to the location of wind turbines, without having to consider new noise receptors;
  • Limiting "stopping the clock" for judicial review, and
  • Natural Heritage Amendments

Re-issuance of draft site plans to reflect changes to the location of wind turbines

As proposed, O. Reg. 359/09 has been amended to:

  • Extend the time to submit an application from 6 months to up to 18 months and permit the issuance of multiple draft site plans within the 18 month period without having to consider new noise receptors since the issuance of the first draft site plan.