ARTICLE · 15 FEBRUARY 2023

Recent Ontario Energy Directive Takes Aim At Province's Looming Power Supply Gap – But At What Cost?

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

The directive orders the procurement of a total 4,000 MW of new electricity supply, including 1,500 MW of new gas-fired generation to be brought in to commercial operation by May of 2026.

CanadaEnergy and Natural Resources

On Oct. 6, 2022, Ontario Minister of Energy, Todd Smith, issued a directive to the Independent Electricity System Operator ("IESO") directing it to procure 4,000 megawatts (MW) of new electricity supply to serve the province's growing electricity needs.

Context

Relying heavily on the IESO's October 2022 Resource Eligibility Interim Report, the October ministerial directive underscores the looming electricity supply shortage risk, which the province now faces after years of power supply contract cancellations and procurement decision delays. The coming power supply gap is indeed driven to some extent by economic growth and population growth but, more fundamentally, it arises due to the expiry of historic power supply contracts and the planned refurbishment requirements of the gigantic Bruce and Darlington nuclear plant facilities – supply factors which were well-understood and long-foreseen by system planners.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from