ARTICLE · 15 JANUARY 2021

Recent Alberta Utilities Commission Decision Brings Retroactive And Prospective Changes For Alberta Distribution Connected Generators

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

McCarthy Tétrault LLP provides a broad range of legal services, delivering strategic and...

View firm profile
Explore more from McCarthy Tétrault

Following the Alberta Utilities Commission's ("AUC") Decision 25848-D01-2020 (the "Decision") late in December 2020 varying Decision 2294-D02-2019 (the "Initial Decision")...

CanadaEnergy and Natural Resources

Following the Alberta Utilities Commission's ("AUC") Decision 25848-D01-2020 (the "Decision") late in December 2020 varying Decision 2294-D02-2019 (the "Initial Decision"), lenders and project developers within Alberta can expect impacts to connection costs for distribution connected generation ("DCG") projects. The Decision approved the Alberta Electric System Operator's ("AESO") proposed adjusted metering practice and use of the substation fraction methodology to allocate the costs of interconnection facilities that may have joint use as part of the 2018 independent system operator tariff (the "ISO Tariff").

The cumulative effects of the Decision for lenders and project developers are not yet fully determined and are anticipated to unfold in the coming months. In the interim, lenders and project developers should consider both the retroactive cost allocation and prospective changes and how these changes may impact current and future projects, including

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from