Share on LinkedInShare on LinkedIn

ARTICLE · 29 AUGUST 2022

Quebec Issues Follow-Up Regulations And Details To Its Announcement Of A 2300 MW Of Renewable Energy RFPs

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

McCarthy Tétrault LLP provides a broad range of legal services, delivering strategic and...

View firm profile
Explore more from McCarthy Tétrault

Last April, the Government of Quebec and Hydro-Québec announced the launch of two new RFPs for a total block of 2,300 MW of renewable energy, which effectively kicked off the largest wind...

CanadaEnergy and Natural Resources

Last April, the Government of Quebec and Hydro-Québec announced the launch of two new RFPs for a total block of 2,300 MW of renewable energy, which effectively kicked off the largest wind and renewable energy procurement project in the Province's history. This is in parallel to the recent two RFPs for 780 MW of renewable energy (where submissions were received last July by Hydro-Québec) as well as the announced three wind projects totalling 1,200 MW to be jointly developed by Boralex, Énergir and Hydro-Québec.

In our previous publication, we indicated that the two RFPs would be led by Hydro-Québec, and that the Government implied that the new RFPs will have a structure similar to that of the current 300 MW and 480 MW RFPs: the 1,000 MW block would be reserved for wind energy, the slightly larger block of 1,300 MW would be open to all forms of renewable energy electricity production, such as solar, biomass, hydroelectric, and wind.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from