On June 22, 2018 the B.C. Supreme Court in Canada (Canadian
Environmental Assessment Agency) v. Taseko Mines Limited 2018
BCSC 1034 took a narrow view of the scope of federal environmental
assessment, leaving it open to the Province of B.C. to authorize
preliminary work in relation to a gold- copper mine project which
had failed to obtain federal environmental assessment approval.
The Federal Designated Project and Provincial Permits
Following an environmental assessment under the Canadian
Environmental Assessment Act (CEAA 2012), the federal
government had rejected a designated project for the construction,
operation and closing of an open pit mine because it was likely to
cause unjustified adverse environmental effects. The designated
project included the open mine pit, a concentration facility,
support infrastructure, associated tailing and waste rock areas,
access road, transmission line corridor, transport of mine
concentrates and any physical activities
"incid