On January 7, 2026, the Ontario government announced that it approved the recommendation of the Independent Electricity System Operator (IESO) to build a new underwater electricity transmission line...

CanadaEnergy and Natural Resources

On January 7, 2026, the Ontario government announced that it approved the recommendation of the Independent Electricity System Operator (IESO) to build a new underwater electricity transmission line from near the Darlington Nuclear Generating Station to the downtown core and eastern portion of the City of Toronto ("Toronto Third Line").

Electricity demand in Toronto is expected to double by 2050 and the City is supplied by two transmission lines that will begin to reach their capacity in the 2030s.

The government's decision to proceed with a third transmission line comes after extensive IESO analysis of options to meet growing electricity demand in Toronto. The IESO's recommendation to proceed with the Toronto Third Line option is detailed in its 2025 Toronto Integrated Regional Resource Plan.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from