The appellants had argued before the AUC that savings arose from the lines having been optimally routed through First Nations lands (i.e. when they were initially constructed) and that intangible...

CanadaEnergy and Natural Resources

ALBERTA

AltaLink Management Ltd. v. Alberta (Utilities Commission), 2021 ABCA 342

As discussed in more detail in our Aboriginal Law article, the Alberta Court of Appeal further clarified the nature of the public interest as it relates to decisions affecting First Nations in AltaLink Management Ltd. v. Alberta (Utilities Commission). In November 2018, the Alberta Utilities Commission (AUC) conditionally approved transfers of electrical transmission assets between AltaLink Management Ltd. and limited partnerships controlled by two Alberta First Nations. The AUC applied a "no harm" test and determined that transfers were in the public interest, though it did not accept arguments to justify passing on the anticipated increased costs (about C$60,000 annually) to ratepayers. The appellants had argued before the AUC that savings arose from the lines having been optimally routed through First Nations lands (i.e. when they were initially constructed) and that

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from