On December 6, 2024, the Government of Alberta (Alberta) approved its anticipated Electric Energy Land Use and Visual Assessment Regulation (Land Use and Visual Assessment Regulation)...

CanadaEnergy and Natural Resources

The New Regulations codify the findings and recommendations from the Alberta Utilities Commission's (AUC) Module A inquiry (the Inquiry). The AUC's Inquiry Report provides summaries of the submissions and observations related to development of specific types or classes of agricultural or environmental land, the impact of power plant development on viewscapes and reclamation security requirements for power plants, development on Crown lands, and the role of municipal governments in the development and review of power plant applications.

Based on the Inquiry and resulting Report, on February 28, 2024, Alberta's Minister of Affordability and Utilities (Minister) issued a policy direction letter to the AUC (the Policy Guidance) announcing the Government of Alberta's six policy and regulatory changes to clarify the rules for future renewable energy projects and developments. A detailed discussion of these policy and regulatory changes are set out in a previous post here.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from