Ontario Energy Board Grants Distribution System Code Exemption For Waterpower Projects

In an oral decision made on May 5, 2011 the Ontario Energy Board granted an application by Ontario Waterpower Association (OWA) for an exemption from sections 6.2.4.1(e) and 6.2.18 of the Distribution System Code (DSC) for hydroelectric projects with a nameplate capacity of between 1 and 10 MW that are located on provincial Crown or federally-regulated lands.

CanadaEnergy and Natural Resources

In an oral decision made on May 5, 2011 the Ontario Energy Board granted an application by Ontario Waterpower Association (OWA) for an exemption from sections 6.2.4.1(e) and 6.2.18 of the Distribution System Code (DSC) for hydroelectric projects with a nameplate capacity of between 1 and 10 MW that are located on provincial Crown or federally-regulated lands.

Section 6.2.4.1(e) of the DSC requires a distributor (in this case Hydro One) to remove an applicant's connection capacity allocation if the applicant has not signed a connection cost agreement (CCA) within 6 months of receiving the allocation.  The provision was introduced in the fall of 2009 to ensure that connection capacity was not tied up by projects that were not being pursued diligently. The Board found there was no evidence that the 28 hydroelectric projects at issue in the application were "laggards" and noted that such projects face unique challenges because of their site-specific nature and the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from