Ontario Court Dismisses Offshore Wind Damages Claim

Trillium Power Wind Corporation (TPWC), the Toronto-based developer interested in building offshore wind turbines in Lake Ontario, is appealing a decision of the Superior Court of Ontario after a judge ruled in favor of the defendant, the province of Ontario, to strike TPWC’s statement of claim.

CanadaEnergy and Natural Resources

Trillium Power Wind Corporation (TPWC), the Toronto-based developer interested in building offshore wind turbines in Lake Ontario, is appealing a decision of the Superior Court of Ontario after a judge ruled in favor of the defendant, the province of Ontario, to strike TPWC's statement of claim.

On October 5, 2012, the Ontario Superior Court of Justice delivered its decision with respect to Trillium Power Wind Corporation v. Ontario (Natural Resources) by striking out the action brought by TPWC against the Ontario government seeking $2.5 billion in damages in relation to the province's February 2011 moratorium on offshore wind farms.

In 2004, TPWC applied to the government of Ontario and was approved by the Ministry of Natural Resources (MNR) as the Applicant of Record to construct and develop an offshore wind farm project in Lake Ontario near Main Duck Island off Prince Edward County, roughly 35 Km south of Kingston. However, in 2006 and then again in 2011, the