Ontario Court Clarifies Degree To Which Municipality Can Restrict A Wind Developer's Use Of Roadways

On August 13, 2015, the Ontario Divisional Court released its decision in Wpd Sumac Ridge Wind Inc. v. Corporation of the City of Kawartha Lakes, 2015 ONSC 4164.

CanadaEnergy and Natural Resources

On August 13, 2015, the Ontario Divisional Court released its decision in Wpd Sumac Ridge Wind Inc. v. Corporation of the City of Kawartha Lakes, 2015 ONSC 4164.1 This decision, which will be welcome news to wind farm developers in Ontario, confirms that municipalities cannot arbitrarily or for an improper purpose deny an approval-holder the use of a roadway that is explicitly referenced in a Renewable Energy Approval (REA).

Wind farm developers typically require usage of municipal roadways for access during construction and operations, including temporary reconstruction or realignment to permit delivery of oversized components such as turbine blades, as well as the installation and maintenance of transmission or distribution infrastructure to connect to the grid.  As a result, a wind farm developer will usually enter into a road use agreement with the affected municipality in order for both parties to clarify their respective rights in coordination with each other. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from