Ontario
announced earlier this week that it would be extending its
moratorium on offshore wind turbine projects. The province had
initially announced the moratorium back in 2011.
The government has indicated that it requires further research
before authorizing the development of off-shore wind farms. Since
the moratorium was put in place, five studies have been
commissioned, with the last two being publicly released in
December. No further studies have been commissioned. The province
appears to be waiting until the impacts of the first off-shore wind
project in the Great Lakes—which has been approved by Ohio
and will be located in Lake Erie—are known.
The province has faced two lawsuits as a result of the initial
moratorium. US company Windstream Energy successfully sued the
province under Chapter 11 of NAFTA, and a tribunal awarded the
company $25 million in damages plus $3 million in legal costs. The
company had planned to build a wind farm in Lake Ontario.