Oil Sands News
1. Cenovus has announced that it is producing
oil from Phase D of its Christina Lake oil sands operation three
months ahead of schedule and within budget. Cenovus commenced
initial steam injection during the second quarter of this year,
with initial production beginning in July. Upon completion,
expected within six to nine months, production from Phase D will be
approximately 40,000 bpd, bringing total production capacity at
Christina Lake to 98,000 bpd. With subsequent expansions and
optimization, it is anticipated that Christina Lake will have an
eventual total production capacity nearing 300,000 bpd.
1. The Alberta Energy Resources Conservation
Board (ERCB) has provided Osum Oil with notice that it has approved
the company's application for the development of a 35,000 bpd
100% owned thermal project near Cold Lake, Alberta. The project
will use both steam assisted gravity drainage and cyclic steam
stimulation recovery processes, and has been