In August 2019, the Ontario Energy Board issued procedural
orders with respect to the hearing of a motion for review of its
earlier decision on an application made by Energy+ Inc. for
approval of an Advanced Capital Module project.
Energy+ requested ACM approval for a proposed capital
expenditure of $8.1 million to renovate and convert an existing
heritage building into an administrative office. In its decision regarding the proposed
project, the OEB applied the three ACM criteria of materiality,
need and prudence. The OEB found that the materiality and need
criteria had been met, but that there was insufficient evidence to
approve a capital budget of $8.1 million as prudent. Among other
things, the OEB expressed concern that the cost estimate was higher
than comparators, that there was significant uncertainty regarding
the cost estimate and about the quality of Energy+’s
estimates. The OEB said that it would approve only $6.5 million for
the ACM, but that Energy+