We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.
ARTICLE · 03 MARCH 2015
New AER Application Requirements Regarding First Nations Consultation To Take Effect March 2

Borden Ladner Gervais LLP
Contributor

Borden Ladner Gervais LLP
With over 750 lawyers, intellectual property agents and other professionals, BLG services...
View firm profileOn February 4, 2015, the Alberta Energy Regulator (the "AER") announced the release of the Joint Operating Procedures for First Nations Consultation on Energy Resource Activities (the "Joint Operating Procedures"), which contain new requirements for applications under the "specified enactments", defined in the Responsible Energy Development Act ("REDA") as the Mines and Minerals Act [Part 8], Public Lands Act, Water Act, and Environmental Protection and Enhancement Act ("EPEA").
CanadaEnergy and Natural Resources