On May 16, 2013, the National Energy Board (“NEB”)
released a decision approving the commercial aspects of the
proposed Trans Mountain pipeline expansion. The NEB was asked to
consider the toll methodology, and terms and conditions that would
apply to the expanded Trans Mountain pipeline (“Trans
Mountain”) if the pipeline's owner, Kinder Morgan Canada,
ultimately decides to undertake the proposed expansion.
According to the decision, the NEB found that the proposed
allocation of capacity between firm service and uncommitted
service, and the proposed allocation of uncommitted capacity
between dock and land destinations, is appropriate. As a result,
the NEB found that Trans Mountain would satisfy its common carrier
obligations. Further, the NEB found that the open season and
negotiation process conducted by Trans Mountain was fair and
transparent and that, on balance, the toll methodology proposed by
Trans Mountain will produce tolls that will be just, reasonable