ARTICLE · 07 SEPTEMBER 2015

Municipalities May Not Exercise Their Powers To Frustrate Projects Granted Renewable Energy Approvals

Municipalities have a right to voice the concerns of their residents with regards to wind turbine projects, but they may not frustrate approved projects when exercising their powers.

CanadaEnergy and Natural Resources

In a recent decision by the Ontario Superior Court of Justice, the court found that the City of Kawartha Lakes had acted outside its jurisdiction and in bad faith when it passed a resolution denying use of a roadway by a wind turbine developer.

Wpd Sumac Ridge Wind Inc. (wpd) obtained a Renewable Energy Approval (REA) for the construction of five industrial wind turbines and associated infrastructure in the City. The roadway was the "spine" of the project. Wpd brought an application for judicial review the City's resolution arguing that the City's conduct of the previous few years, culminating in and evidenced by the resolution, left no doubt of the City's opposition to and intention to prevent the construction of the project. Wpd claimed that the City had deliberately frustrated the REA and acted in bad faith in denying wpd the use of a roadway.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from