ARTICLE · 09 MAY 2014

Joint Review Panel Releases Report On Site C Clean Energy Project

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

Built on a unique model of collaboration, innovation and efficiency, McCarthy Tétrault delivers...

View firm profile
Explore more from McCarthy Tétrault

The report of the joint federal-provincial panel appointed to review BC Hydro’s proposed Site C Clean Energy Project was publicly released.

CanadaEnergy and Natural Resources

Today, the report of the joint federal-provincial panel (the Joint Review Panel) appointed to review BC Hydro's proposed Site C Clean Energy Project (Site C) was publicly released, following its submission to the federal and BC governments on May 1, 2014. A copy of the full report is available here; a copy of the report summary and list of recommendations is available here.

The Joint Review Panel was mandated by Canada's Minister of the Environment and BC's Minister of Environment to assess Site C's potential environmental, economic, social, heritage and health effects.

Among other findings, the Joint Review Panel concluded that:

  • it was unable to assess the accuracy of Site C project cost estimates, and recommended that such costs, including unit energy costs and revenue requirements, be referred to the BC Utilities Commission for detailed examination if Site C proceeds;