ARTICLE · 12 FEBRUARY 2021

Is New England Clean Energy Connect Québec's Keystone XL?

A U.S. court has issued an injunction suspending construction of New England Clean Energy Connect (NECEC), a 1,200 MW transmission project from Québec to Massachusetts by way of Lewiston, Maine.

CanadaEnergy and Natural Resources

A U.S. court has issued an injunction suspending construction of New England Clean Energy Connect (NECEC), a 1,200 MW transmission project from Québec to Massachusetts by way of Lewiston, Maine. The project, which would transmit electricity purchased from Hydro-Québec pursuant to a 20-year 9.45 TWh per year purchase agreement, will now be delayed – a setback for proponents of Québec hydro power as a green alternative in the U.S. Northeast.

Project Background

The project requires the construction of 233 km of high voltage transmission lines mostly following existing power rights-of-way, with only about 85 km being on a new right-of-way to be cut through working forest lands from Forks, Maine up to the Québec border. Interestingly, the right-of-way will be much narrower than what is usually provided, substantially reducing the environmental footprint of the new-built line.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from