On January 27, 2016 the Government of Canada (Government) announced new interim rules which will guide federal decision-making on natural resource projects.

CanadaEnergy and Natural Resources

On January 27, 2016 the Government of Canada (Government) announced new interim rules which will guide federal decision-making on natural resource projects. These rules will apply until the Government's formal review of the federal environmental assessment legislation and the National Energy Board's (NEB) process, announced in December, 2015, is complete. While the Government has not yet announced any of the specific measures it plans to take to overhaul the existing system, it is expected to take several years. In the meantime, the federal interim review process will be undertaken as the Government's second review step, after the NEB has reviewed and approved a project.

The Government's stated reason behind the proposed review of federal environmental assessment process, and the interim rules, both of which will operate separately from, and in addition to, the NEB's review process, is to "restore lost confidence" in the regulatory regime. The NEB's role with respect

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.