ARTICLE · 15 MARCH 2018

Implementing The Province's Long-Term Energy Plan: 3 Things To Bear In Mind

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

On February 21st, the Ontario Energy Board (OEB) posted its Implementation Plan for the Ontario government's Long Term Energy Plan.

CanadaEnergy and Natural Resources

In July 2016, Ontario's Liberal government amended the Electricity Act to (finally) dismantle the previous "Integrated Power System Plan" (IPSP) promulgation and public review mechanism. Despite having been in place for several years, that mechanism had never been fully implemented. The IPSP mechanism was formally replaced with a new energy planning regime under which:

  1. The Minister of Energy publishes a Long Term Energy Plan (LTEP), and issues directives to each of the OEB and the IESO "setting out the Government of Ontario's requirements respecting the implementation of the [LTEP]"; and
  2. Each of the OEB and the IESO are required to formulate and submit for Ministerial approval Implementation Plans "containing an outline of the steps [they] intend to take to meet the requirements set out in the directive".