Share on LinkedInShare on LinkedIn

ARTICLE · 07 AUGUST 2012

Energy @ Gowlings: July 26, 2012 - Volume 10, Number 11

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

On July 11, 2012 Ontario's Minister of Energy issued a directive (directive) to the Ontario Power Authority (OPA) clarifying certain policies and slightly adjusting the feed-in tariff (FIT) program rules and contract.

CanadaEnergy and Natural Resources

Edited by Paul H. Harricks

Ontario Re-Boots FIT 2.0 With Ministerial Directive

Introduction

On July 11, 2012 Ontario's Minister of Energy issued a directive (directive) to the Ontario Power Authority (OPA) clarifying certain policies and slightly adjusting the feed-in tariff (FIT) program rules and contract. The directive was issued following the Ontario government's review of feedback regarding the draft rules, contract forms and definitions for the revised FIT 2.0 program issued in April of this year.

Summary of the Directive's Key Points:

i. Prioritization of Community and Aboriginal Participation Projects

The ministerial directive clarified that the OPA will prioritize applications for projects with (a) greater than 50 per cent community equity interest held by a co-operative with at least 50 members being local property owners, or (b) greater than 50 per cent Aboriginal equity participation. With respect to the contract capacity set aside for projects with at least 50 per

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from