In issuing an electricity transmitter licence to Chatham-Kent Transmission Inc. (CKT), the Ontario Energy Board made some important comments that will be of interest to any transmitters seeking to participate in the Board's upcoming transmitter designation process for the East-West Tie.

CanadaEnergy and Natural Resources

In issuing an electricity transmitter licence to Chatham-Kent Transmission Inc. (CKT), the Ontario Energy Board made some important comments that will be of interest to any transmitters seeking to participate in the Board's upcoming transmitter designation process for the East-West Tie.

While the primary purpose of CKT's application was to own and operate a transmission line that will connect a wind generation facility within the Municipality of Chatham-Kent to the grid, CKT also indicated its longer term intention to participate in the Board's transmitter designation process. A number of intervenors questioned whether CKT had the financial and technical capability to qualify for a full transmitter licence and requested that the licence be limited to the specific facility proposed by CKT.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from