ARTICLE · 16 DECEMBER 2014

Court of Appeal Confirms The AUC's Authority To Award Costs

The Court of Appeal released its decision in ATCO Gas and Pipelines Ltd. v. Alberta (Utilities Commission), 2014 ABCA 397.

CanadaEnergy and Natural Resources

On December 2, 2014 the Court of Appeal released its decision in ATCO Gas and Pipelines Ltd. v. Alberta (Utilities Commission), 2014 ABCA 397. Chief Justice Fraser, along with Justice Côté, dismissed ATCO's appeal of the Commission's costs award (Justice Martin dissenting in part). The decision affirms the Commission's authority to exercise discretion in awarding costs to both interveners and utilities.

FACTS

ATCO Gas and Pipelines Ltd. and ATCO Electric Ltd. (collectively "ATCO"), appealed two cost decisions issued by the Alberta Utilities Commission ("Commission"). The decisions related to ATCO's involvement in the Utility Asset Disposition Proceeding ("UAD") and the Performance-Base Reform Proceeding (PBR). Both proceedings were initiated by the Commission. Neither was a rate setting hearing. The UAD proceeding considered the implications of the Supreme Court of Canada's decision in ATCO Gas and Pipelines Ltd. v. Alberta (Energy and Utilities Board). The PBR

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from