ARTICLE · 13 DECEMBER 2021

Canada Energy Regulator Rejects Proposal For Firm Service On Enbridge's Canadian Mainline

On November 26, 2021, the Commission of the Canada Energy Regulator (the Commission) issued its Reasons for Decision in Enbridge Pipelines Inc. RH-001-2020 (the Decision)...

CanadaEnergy and Natural Resources

Introduction

On November 26, 2021, the Commission of the Canada Energy Regulator (the Commission) issued its Reasons for Decision in Enbridge Pipelines Inc. RH-001-2020 (the Decision), denying the application of Enbridge Pipelines Inc. (Enbridge) to introduce firm service on the Canadian Mainline (the Application). If approved, the Application would have made 90% of the Canadian Mainline's currently uncommitted capacity subject to firm contracts for priority access, with contract terms ranging from eight to 20 years. Contracts for firm service were to be awarded through an open season process put forward as part of the Application.

In its reasons for denying the Application, the Commission provided much-needed guidance on what is entailed by a pipeline operator's common carriage and non-discrimination obligations under the Canadian Energy Regulator Act (the CER Act), and confirmed the importance of cost information in assessing whether tolls will be just and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from