Bringing A Positive Charge Back To Ontario's Housing Economy: Province & OEB Announce Efforts To Reduce Regulatory Barriers And Costs For Housing Developers

McMillan LLP
McMillan LLP
Contributor
McMillan LLP

McMillan LLP

The firm : McMillan LLP is one of Canada’s leading national law firms with offices in Montreal,...

View firm profile
Explore more from McMillan LLP

On November 18th, the Ontario Energy Board ("OEB") published a Notice of proposed amendments to the Distribution System Code ("DSC"), which amendment are intended to facilitate the connection...

CanadaEnergy and Natural Resources

On November 18th, the Ontario Energy Board ("OEB") published a Notice of proposed amendments to the Distribution System Code ("DSC"), which amendment are intended to facilitate the connection of housing developments in Ontario. The amendments will, for "qualifying housing developments", increase the forecast period which electricity utilities apply in estimating revenues from a system expansion, which in turn will reduce the payments that developers have to contribute to offset the utilities potential losses. Specifically, going forward, the connection forecast horizon can be up to 15 years instead of 5 years, and the revenue forecast horizon will be 40 years instead of 25 years.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The foregoing provides only an overview and does not constitute legal advice. Readers are cautioned against making any decisions based on this material alone. Rather, specific legal advice should be obtained.