Arising out of Alberta Utilities Commission (AUC) Module A Inquiry and the AUC's resulting report, the Government of Alberta (Alberta)...

CanadaEnergy and Natural Resources

Arising out of Alberta Utilities Commission (AUC)  Module A Inquiry and the AUC's resulting report, the Government of Alberta (Alberta) announced plans to implement policy and regulatory changes for future renewable power generation projects.These changes were announced by Alberta's Minister of Affordability and Utilities (Minister) on the eve of the expiration of the seven-month moratorium on approving wind and solar projects imposed under the Generation Approvals Pause Regulation.

Confirming the expiration of the pause on AUC approvals of new renewable generation projects, the announced policy and regulatory changes can be summarized as:

  1. taking an “agriculture-first” approach to project approval;

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from