Appeal Court Allows $2-Billion Wind Farm Action To Proceed Against Government Of Ontario

On November 12, 2013, inTrillium Power Wind Corporation v. Ontario (Natural Resources), 2013 ONCA 683, the Ontario Court of Appeal allowed a $2-billion action by Trillium Power Wind Corporation (Trillium) to proceed against the Government of Ontario as a result of the government’s decision in 2011 to impose a moratorium on offshore wind power development.

CanadaEnergy and Natural Resources

On November 12, 2013, in Trillium Power Wind Corporation v. Ontario (Natural Resources), 2013 ONCA 683, the Ontario Court of Appeal allowed a $2-billion action by Trillium Power Wind Corporation (Trillium) to proceed against the Government of Ontario as a result of the government's decision in 2011 to impose a moratorium on offshore wind power development. The Court allowed Trillium's claim to proceed on the sole, narrow basis that the government had, allegedly, committed "misfeasance in public office" because, in imposing the moratorium when it did, the government had allegedly targeted Trillium, intending to cause Trillium harm.  However, the Court did not allow Trillium to proceed with its other claims based upon, among other things, breach of contract and negligence.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from