An Update On The IESO's LT1 RFP In Ontario

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

Built on a unique model of collaboration, innovation and efficiency, McCarthy Tétrault delivers...

View firm profile
Explore more from McCarthy Tétrault

As part of the IESO's engagement on the Long Term RFP, the IESO hosted a webinar today regarding the LT1 RFP. Consistent with previous announcements, the IESO currently anticipates that it will procure 2,200 MW...

CanadaEnergy and Natural Resources

As part of the IESO's engagement on the Long Term RFP, the IESO hosted a webinar today regarding the LT1 RFP. Consistent with previous announcements, the IESO currently anticipates that it will procure 2,200 MW of capacity under the LT1 RFP (of which 1,600 MW is expected to be storage) and that the LT1 Contracts will have a 20 year term. The IESO outlined the following expected timelines for the LT1 RFP:

2023

  • March – Launch of LT1 RFP
  • Mid-April – Deliverability Test Report
  • May – Issuance of Draft LT1 RFP and Contract
  • Mid-May – Updated Deliverability Guidance Document (including changes to test assumptions and locational preference considerations)
  • July - Preliminary Deliverability Test

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from