ARTICLE · 25 OCTOBER 2016

Alberta Utilities Commission Confirms It Has No Jurisdiction To Assess Crown Consultation

On October 7, 2016, AUC confirmed it has no jurisdiction to consider or assess the adequacy of Crown consultation with Aboriginal groups that may be affected by a project under review.

CanadaEnergy and Natural Resources

On October 7, 2016, the Alberta Utilities Commission (AUC or Commission) confirmed it has no jurisdiction to consider or assess the adequacy of Crown consultation with Aboriginal groups that may be affected by a project under review. The ruling was issued as part of the AUC's process to consider the Fort McMurray West 500-kV Transmission Project (AUC Proceeding 21030) and marks the first occasion that the Commission has explicitly considered and ruled on this jurisdictional issue. Subject to any appeals, this ruling will help guide the scope of future facilities proceedings before the AUC.

Background

Over the last several years, the issue of whether a tribunal has the jurisdiction to review and consider Crown consultation with Aboriginal groups has arisen in several contexts in Alberta. Much of the debate has followed the 2010 Supreme Court of Canada ruling in Rio Tinto Alcan Inc v Carrier Sekani Tribal Council, 2010 SCC 43 (Carrier Sekani), which found that the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from