On February 28, 2024—the day before the expiration of the moratorium on the approval of renewable power projects—the Government of Alberta announced a host of prospective policy...

CanadaEnergy and Natural Resources

On February 28, 2024—the day before the expiration of the moratorium on the approval of renewable power projects—the Government of Alberta announced a host of prospective policy and regulatory changes for renewable power development in the province.

What you need to know

  • Agriculture-first approach. Renewable power development will no longer be permitted on Class 1 and Class 2 agricultural lands unless the proponent can demonstrate the ability for agriculture to coexist with the renewable power project and that agricultural land uses will generally be prioritized in the processing of renewable power applications.
  • Buffer zone. A 35-kilometre buffer zone will be implemented around areas designated as "pristine viewscapes", which will preclude wind and potentially other renewable power developments.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from