The Alberta Government's pause on approving renewable energy
projects in the province1 ended on February 29,
2024 when the Generation Approvals Pause
Regulation expired.
On February 28, 2024, Premier Danielle Smith and Utilities
Minister Nathan Neudorf announced details of proposed policy
changes that are intended to support the ongoing economic, orderly
and efficient development of electricity generation in
Alberta.2
Shortly after the pause began, the Alberta Utilities Commission
("AUC") established two modules to consider issues
relating to renewable energy project development in the
province.
Module A focused on land use issues identified by the
Government's order-in-council, including in
particular:3