Alberta Court Overturns Ministerial Decision On Oil Sands Cost Recovery

Blake, Cassels & Graydon LLP
Blake, Cassels & Graydon LLP
Contributor
Blake, Cassels & Graydon LLP

Blake, Cassels & Graydon LLP

As one of Canada’s top business law firms, Blake, Cassels & Graydon LLP (Blakes) provides...

View firm profile
Explore more from Blake, Cassels & Graydon LLP

There is no appeal pending and the period of appeals has expired.

CanadaEnergy and Natural Resources

On judicial review, the Alberta Court of Queen's Bench overturned a ministerial decision of the Alberta Department of Energy (ADOE) regarding costs incurred by an oil sands project owner in Fort Hills Energy Corporation v. Alberta (Minister of Energy). The case was decided on a standard of reasonableness and is the first to interpret and articulate the underlying policy of some of the relevant cost recovery rules.

The court found that the Minister of Energy's decision to disqualify C$791,831,844 in project development costs incurred by the project owner was unreasonable and quashed the Minister's decision on this point. There is no appeal pending and the period of appeals has expired.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

For permission to reprint articles, please contact the [email protected] Marketing Department.

© 2026 Blake, Cassels & Graydon LLP.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from