Alberta's "30 By 30" Renewable Energy Target: Will Wind Energy Projects Now Be Permitted On Public Lands?

Blake, Cassels & Graydon LLP
Blake, Cassels & Graydon LLP
Contributor
Blake, Cassels & Graydon LLP

Blake, Cassels & Graydon LLP

As one of Canada’s top business law firms, Blake, Cassels & Graydon LLP (Blakes) provides...

View firm profile
Explore more from Blake, Cassels & Graydon LLP

On September 14, 2016, the Alberta government provided an update regarding its Renewable Electricity Program.

CanadaEnergy and Natural Resources

On September 14, 2016, the Alberta government provided an update regarding its Renewable Electricity Program. In particular, the government confirmed a firm target of 30 per cent electricity from renewable sources by 2030 (30 by 30) and announced that it will support the development of 5,000 megawatts (MWs) of additional renewable energy capacity to help achieve this target. Further details pertaining to how projects will be selected and what financial support will be provided to incentivize renewable development won't be available until November.

Notwithstanding the lack of clarity around project selection, it is anticipated that a significant portion of the additional 5,000 MWs of renewable energy capacity will come from wind power. The focus of policy discussions for achieving these renewable energy targets has to date been on the establishment of economic conditions to incentivize such development. Little attention has to this point been given to the issue of