AESO Cuts $1 Billion From Transmission Budget Forecast

Alberta Electric Systems Operator (AESO) forecasts the province will spend $13.5 billion in the next decade to keep pace with growth in electricity demand.

CanadaEnergy and Natural Resources

Alberta Electric Systems Operator (AESO) forecasts the province will spend $13.5 billion in the next decade to keep pace with growth in electricity demand. Within 20 years, Alberta will require 13,000 megawatts of new generation capacity, with much of the growth fuelled by oilsands developments.

However, AESO reduced the province's planned expenditures by $1 billion compared to its 2009 draft budget by eliminating or reducing the scale of certain projects. In the latest forecast, $8.3 billion will be committed towards 50 regional projects serving 200 customer connections. The remaining $5.2 will be directed towards four transmission infrastructure projects outlined in The Electric Statutes Amendment Act, 2009.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from