In carrying out its powers, duties and functions, the Alberta Energy Regulator is obligated to act in accordance with any applicable regional plan made pursuant to the Alberta Land Stewardship Act.

CanadaEnergy and Natural Resources

In carrying out its powers, duties and functions, the Alberta Energy Regulator (AER) is obligated to act in accordance with any applicable regional plan made pursuant to the Alberta Land Stewardship Act (ALSA). In its AER Bulletin 2014-28, the AER has provided guidelines for applicants to assist both the applicants and the AER to ensure that energy development complies with ALSA regional plans. These guideline requirements will be incorporated into all applicable AER directives and guides. A full copy of AER Bulletin 2014-28 can be accessed here.

AER Bulletin 2014-28: Application Requirements for Activities within the Boundary of a Regional Plan

On September 19, 2014, the AER has announced measures it will take to ensure it meets its statutory obligation to act in compliance with regional plans under the ALSA. Applications seeking approval from the AER for an activity that is to be located within the boundary of an approved regional plan, as set out under the ALSA,m