ARTICLE · 21 APRIL 2020

Timelines For Alberta Builders' Liens During The COVID-19 State Of Emergency

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

Due to the state of public emergency in Alberta arising from the COVID-19 pandemic, on March 30, 2020, the Minister of Justice and Solicitor General of Alberta issued a Ministerial Order which suspended the operation...

CanadaCoronavirus (COVID-19)

As of April 9, 2020

Due to the state of public emergency in Alberta arising from the COVID-19 pandemic, on March 30, 2020, the Minister of Justice and Solicitor General of Alberta issued a Ministerial Order which suspended the operation of limitation periods for a list of certain enactments.

This raises important questions of what timelines apply in Alberta with respect to unlisted statutes, such as the Builders' Lien Act and the Public Works Act during the COVID-19 state of emergency.

Key provisions of ministerial order

The Ministerial Order includes three key provisions, and states:

  1. Limitation periods are suspended in the enactments under Appendix A from March 17, 2020 to June 1, 2020.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.