Mr Holm (Holm) brought proceedings against the appellants for damages for breach of contract for his investment in the Bank of Asia Project (Project). The claim was bifurcated with Holm succeeding on liability.

British Virgin IslandsFinance and Banking

Court: Eastern Caribbean Court of Appeal

Subject: Interim payment order under CPR Rule 17; 'reasonable proportion' in interim payments; inability to pay interim payments

Judges: Hon. Mde. Ellis, Hon. Mde. Alexander, Hon. Mr. Ramdhani

Summary

Mr Holm (Holm) brought proceedings against the appellants for damages for breach of contract for his investment in the Bank of Asia Project (Project). The claim was bifurcated with Holm succeeding on liability.

With liability settled, Holm successfully applied under Rule 17.5 of the Civil Procedure Rules (Revised Edition) 2023 (CPR) for an interim payment of damages of an amount considered the 'irreducible minimum'. The grounds of appeal included that the learned judge wrongly determined the 'reasonable proportion' of the overall damages likely to be awarded to the respondent at the quantum trial, and erred in concluding that any interim payment should be made, in disregarding the need for Holm to show that he had

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from