EIAs: Grubbing Ups And Path Clearances For Overhead Electrical Power Lines To Be Treated Differently

Schoenherr (Schönherr Rechtsanwälte)
Schoenherr (Schönherr Rechtsanwälte)
Contributor
Schoenherr (Schönherr Rechtsanwälte)

Schoenherr (Schönherr Rechtsanwälte)

Schoenherr is a leading European full-service law firm with a strong footprint across Central and...

View firm profile
Explore more from Schoenherr (Schönherr Rechtsanwälte)

When it comes to clearing a path in a forest to construct and operate an overhead electrical power line, electricity grid operators face various legal issues.

AustriaEnvironment

Introduction

When it comes to clearing a path in a forest to construct and operate an overhead electrical power line, electricity grid operators face various legal issues.

The clearance of a path involves felling trees underneath power lines to guarantee a minimum safe distance from the electric cables.

In recent years, the crucial legal question has been whether such path clearances must be considered when determining whether a specific project (ie, the installation of electrical power lines) is subject to an Environmental Impact Assessment (EIA).

While the European Court of Justice (ECJ) clarified this issue in 2018 (at least for non-governmental organisations), in light of the applicable EU EIA Directive (2011/92/EU),1 it remains unclear whether grubbing ups and path clearances should be treated in the same way in terms of their respective environmental impacts. In particular, must the permitting requirements of the Austrian Forestry Act2 stipulated for

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from