When are liquidated damages in reality a penalty and therefore not enforceable?

Liquidated damages are often resisted by contractors, on the basis that the liquidated damages rate is really a penalty.

AustraliaReal Estate and Construction

Liquidated damages are pre-agreed fixed damages payable by one party to another as a means of compensation for loss or damage suffered following a breach of a contract.

The breach triggering the payment of liquidated damages must be one which would normally cause damage to the party in whose favour the liquidated damages apply.

By agreeing to the amount or rate of liquidated damages, the parties agree at the time of entering into the contract, the rate at which damages will be payable following the occurrence of the identified breach.

Construction contracts often use liquidated damages.

If the party undertaking the construction works (the contractor) breaches the contract by failing to complete the construction works within the period or by the date required by the contract (i.e. by the date for practical completion) then the contractor must pay damages for that breach to the other party (the principal or developer).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from