What to include in a Show Cause Notice under a Construction Contract

A show cause notice must comply with the requirements of the intended contract and convey to the reader what is amiss.

AustraliaReal Estate and Construction

In Dura (Aust) Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3) [2012] VSC 99 the Victorian Supreme Court has recently provided guidance on both the required content of show cause notices under construction contracts and what a Principal must consider when evaluating whether cause has been shown by a Contractor responding to such a notice.

Facts

Hue Boutique Living Pty Ltd (Hue), the Principal, engaged Dura (Aust) Constructions Pty Ltd (Dura), the Contractor, under an AS 2124 - 1992 (the Contract), to build an apartment block in Richmond, Melbourne. Hue served 4 show cause notices on Dura under clause 44.2 of the Contract, alleging that Dura was in default by separate substantial breaches of the Contract and requiring Dura to show cause in writing why Hue should not exercise a right under the Contract to either take the works out of the hands of the Contractor or terminate the contract (if the Contractor fails to show reasonable cause by the time specified in

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from